Interconnection strategy
A practical interconnection strategy connects project size and operating assumptions with utility requirements, study processes, schedule, cost, and deliverability.
Grid Infrastructure
Generation creates value only when it can interconnect safely, reliably, and economically with the power system.
Grid Infrastructure
A practical interconnection strategy connects project size and operating assumptions with utility requirements, study processes, schedule, cost, and deliverability.
Substation scope may include site planning, equipment configuration, protection, controls, communications, civil work, testing, and interfaces with utilities and generating facilities.
Transmission development requires corridor, right-of-way, permitting, geotechnical, structural, electrical, access, construction, and stakeholder coordination.
Protection, metering, communications, supervisory control, and operating procedures must function across the project, substation, utility, and system-operator boundaries.
Substations are where a project meets the network, and where a permitting or equipment lead time most often becomes the critical path. Layout, voltage, and protection philosophy are set early because they constrain everything from land take to commissioning.
Routing a line is a land, environmental and constructability problem as much as an electrical one. Alignment decisions made early determine the easements required and the objections likely to arise.
Grid
728 MW
Capacity connected
Across the recorded portfolio
8 countries
Interconnection regimes
Each with its own utility process
IEEE 1547
Interconnection standard
Distributed interconnection requirements
3 continents
Grid environments
North America, Asia, Africa
Grid scope across the recorded portfolio and the standards that govern it.
Common questions
Clear answers
The scope may include interconnection studies, substations, transmission or distribution upgrades, protection, controls, metering, communications, land, permitting, testing, and utility coordination.
Study timelines, network upgrades, equipment lead times, cost allocation, operating limits, and utility requirements can affect feasibility, schedule, and economics.
It should begin early enough to inform land needs, site layout, interconnection scope, major equipment procurement, permitting, construction sequencing, and commissioning.
Both. The distinction changes the standards, witness testing and approval path, so it is established at the outset rather than assumed.
Power transformers and high-voltage switchgear, and in current market conditions the lead times on both should be assumed to drive the programme unless confirmed otherwise.
Yes. Existing queue positions are assessed for what they actually secure, what the study results imply for upgrade cost, and what the milestone obligations require to keep the position alive.
Grid infrastructure
Voltage, location, utility, and what the interconnection currently requires.
Email TransGlobe PowerStart a conversation
Share the voltage, location and utility. We will work through what the connection requires.
Discuss a project